Extracted standards
3 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Battery energy storage systems
Battery energy storage systems are considered accessory uses when designed to serve the principal use only and not the electric power grid, and must comply with applicable codes.
- Portable on demand storage units6 months
Portable on demand storage (POD) units are permitted for a total of six months, after which a zoning permit must be obtained.
- Solar collector setbacksSetbackThe distance a building must be held back from a lot line.10 ft
Ground-mounted solar collectors shall not be located within ten feet of any side or rear lot line. Ground-mounted solar collectors in a front yard shall meet the minimum setback for the principal structure. Maximum height of ground-mounted solar collector is 15 feet.
From the ordinance
Portable on demand storage (POD) units shall be considered a temporary structure. They are permitted for use for a total of six months, after which a zoning permit must be obtained. Distributed solar energy facility shall be considered an accessory use... Ground-mounted solar collectors shall not be located within ten feet of any side or rear lot line. The maximum height of a ground-mounted solar collector shall be 15 feet.