Extracted standards
6 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- AgriculturalAgricultureRaising crops or livestock, generally including the structures that serve them. restoration
For facilities located in the A-R district, at the completion of decommissioning, the properties shall be returned to a state in which agricultural or forestal use may continue in order to preserve and protect the county's rural and agricultural character.
- Decommissioning timeline6 months
The decommission process shall occur within six months after the battery energy storage system permanently ceases operation.
- Decommissioning trigger6 months
If the facility ceases to generate electricity for more than six consecutive months, unless due to an act of God, the responsible party will provide for its decommissioning.
- Phase II environmental site assessment
Upon completion of decommissioning, the project owner or operator shall provide to the planning director a report detailing compliance with all of conditional use permit and ordinance requirements required for decommissioning as well as perform and provide a phase II environmental site assessment report of the site to the county.
- Foundation removal
The removal from the surface of the property, any project facilities and appurtenances installed or constructed thereupon, including permanent foundations shall be completed both above and below ground. For facilities located in an M-1 or M-2 district, foundations shall be permitted to remain.
- Surety amount120 pct
The amount of the surety required shall be 100 percent of the estimated decommissioning costs plus 20 percent in administrative fees.
From the ordinance
If the facility ceases to generate electricity for more than six consecutive months, unless due to an act of God, the responsible party will provide for its decommissioning.