- Conditional useConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. permit commencement time limit24 months
Any conditional use permit granted shall be null and void 24 months after approval by the town council if the use or development authorized by the permit is not commenced...
- Conditional useConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. permit extension period12 months
The property owner, or applicant, may request that town council allow a 12-month extension beyond the 24 month period...
- NonconformingNonconformingLawful when built, but not compliant with the rules now in force; usually allowed to continue but not to expand. use discontinuation period24 months
Activities or uses approved by a conditional use permit which are discontinued for a period of more than 24 consecutive months shall not be reestablished...
- Non-residential daily trip threshold for traffic impact statement2,500 trips
2,500 vehicle trips per day by non-residential development
- Non-residential peak hour trip threshold for traffic impact statement250 trips
250 vehicles trips per peak hour by non-residential development
- Residential peak hour trip threshold for traffic impact statement100 trips
100 vehicles trips per peak hour by residential development
From the ordinance
Any conditional use permit granted shall be null and void 24 months after approval... Activities or uses approved by a conditional use permit which are discontinued for a period of more than 24 consecutive months shall not be reestablished... traffic impact statement whenever... 100 vehicles trips per peak hour by residential development; 250 vehicles trips per peak hour by non-residential development; 2,500 vehicle trips per day by non-residential development.