Dimensional standards
Extracted standards
19 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Density
- Maximum percentage of townhousesTownhouseA single-family home sharing side walls with its neighbours, each on its own lot., two-family, and attached combined50 pct
Townhouses, two-family dwellings, and single-family attached, combined shall constitute a maximum of fifty (50) percent of the dwelling units in any subdivision.
Design
- Principal orientation parallel to street
Except in the MXD District, the principal orientation of each residential unit shall be parallel to the street it faces. The street elevation of each residential unit shall have at least one (1) street oriented entrance, and contain the principal windows of the unit.
- Street-oriented entrance
The street elevation of the residential buildings shall have at least one (1) street-oriented entrance, and contain the principal windows of the front unit.
Other
- Final plat after foundation
The final subdivision plat shall not be submitted for review until the foundation has been constructed. The final subdivision plat must be submitted within twelve (12) months of the approval of the preliminary plat.
- HistoricHistoric districtAn area where exterior changes need design review to protect its character. or design review board review in R-5
The historic or design review board shall review all building permit applications and make recommendations to the applicant and Zoning Administrator for amendments to achieve consistency with this Section. These recommendations are advisory only.
- Minimum open spaceOpen spaceLand a development must leave unbuilt, sometimes required to be usable or planted. for 5+ two-family dwellings20 pct
Except in the MXD District, for any development of five (5) or more two-family attached dwellings, a minimum of twenty (20) percent of the gross land area shall be reserved as open space for community recreation use.
- Neighborhood compatibility in OTR
Applicants must clearly demonstrate that the use will be compatible with the neighborhood, particularly with regard to traffic circulation, parking, and appearance.
- Neighborhood compatibility in R-5
The applicant must clearly demonstrate that the use will be compatible with the neighborhood, particularly with regard to traffic circulation, parking, and appearance.
- Parking lot landscaping in R-55 pct
Parking lot landscaping: Five (5) percent of the parking lot shall be landscape with trees and groundcover.
- Retention of existing structures encouraged in OTR
The retention and use of existing structures that contribute to the character of the neighborhood is encouraged.
- Sidewalks connect units
Sidewalks shall connect each unit to the parking area serving that unit, to other units on-site, and to other buildings or uses on adjacent lots.
- Street trees in R-51 tree per 30 ft of road frontageFrontageThe length of a lot line that touches a public street.
Street trees: One (1) tree per thirty (30) feet of road frontage.
- Subdivision plat required
A subdivision plat shall be submitted with the site development plan or with the Conditional Use Permit application, where individual attached units are to be constructed on individual lots. The subdivision plat shall meet the standards of the Subdivision Ordinance, except the dedication of park land shall not be required in the MXD District or when twenty (20) percent of the area is reserved as open space per subsection (3), above.
- Trash and mechanical equipment screening
Trash dumpsters, trash containers, recycling containers, and mechanical equipment shall be screened per the requirements of Article V.
- Tree canopy coverage in R-520 pct
Tree canopy coverage: R-5 requirement is twenty (20) percent.
- Tree replacement requirement in R-5
Tree replacement requirement: Any trees on the site which are a caliper of five (5) inches or more at a height of one (1) foot above the ground, or ornamental trees over twelve (12) feet in height which are to be removed during site development shall be replaced.
- Type A buffer yardYardThe open space left between a building and its lot line — the space a setback creates. required in OTR
A type A buffer yard shall be required on any lot which abuts the R-4, R-5, OTR, PR, RR1, or RR2 zoning district.
Parking
- Parking behind front building line
All parking spaces shall be located behind the front building line. Town Council may grant a special exception to this requirement as authorized by Section 1112. Shared driveways are permitted, with the recordation of perpetual easements to provide for the use and maintenance of the shared driveway. Courtyard style parking is permitted, as is the use of alternative pavements, such as brick pavers or porous pavement.
Setback
- Minimum side setbackSetbackThe distance a building must be held back from a lot line. in OTR15 ft
Minimum side setback: Fifteen (15) feet.
From the ordinance
Except in the MXD District, the principal orientation of each residential unit shall be parallel to the street it faces.