Extracted standards
3 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- No increase in nonconformity
No nonconforming structure may be altered in a way which increases the nonconformity.
- Repair start time180 days
Reconstruction must start within 180 days from date of damage.
- Repair threshold50 pct
If cost of restoring does not exceed 50% of current assessed value, structure may be restored to original nonconforming condition.
From the ordinance
No nonconforming structure may be altered in a way which increases the nonconformity. ... if a nonconforming structure is destroyed or damaged, and the cost of restoring the structure to its condition does not exceed fifty (50) percent of current assessed value of the entire structure, then the structure may be restored to its original nonconforming condition, provided that a building permit is secured, reconstruction is started within one hundred eighty (180) days from the date of the damage, and such reconstruction is diligently pursued to completion.