Floodplain
- Base flood elevation determination
When elevations cannot be determined by using other sources of data, then the applicant for the proposed use, development or activity, with the assistance of the county shall determine an elevation using technical concepts such as point on boundary, high water marks, or hydrologic and hydraulic analysis.
- Lowest floor elevation
When such base elevation has been determined, the lowest first finished floor shall be elevated to or above the base flood elevation and meet the floodproofing requirements for elevated structures.
- No development increasing flood heights
Until a regulatory floodway is designated no new construction, substantial improvements, or other development including fill, will be permitted within these areas until it has been demonstrated that the cumulative effect of the proposed development will not increase the water surface elevation of the base flood more than one foot at any point.
Other
- Alteration of watercourses requires approvals
Prior to any proposed alteration or relocation of any channels, floodways or any watercourse... approval shall be obtained from the U.S. Corps of Engineers, Virginia Department of Environmental Quality, and the Virginia Marine Resources Commission.
- Anchoring of new construction
New construction and substantial improvements shall be anchored to prevent flotation, collapse or lateral movement of the structure...
- Site plan information required
All applications for development within any floodplain district... shall incorporate: the elevation of the base flood at the site, the elevation of the lowest floor, etc.
- Preservation of drainageways
Under no circumstances shall any use, activity or development adversely affect the capacity of the channels or floodways of any watercourse, drainage ditch or any other drainage facility or system.
- Utilities designed to prevent water entry
Utilities and mechanical devices and equipments and other service facilities shall be designed or located as to prevent water from entering or accumulating within the components during flooding.
From the ordinance
These areas are shown as a zone A on the flood insurance rate maps and no detailed flood profiles or elevations are provided. When elevations cannot be determined by using other sources of data, then the applicant... shall determine an elevation using technical concepts... When such base elevation has been determined, the lowest first finished floor shall be elevated to or above the base flood elevation and meet the floodproofing requirements for elevated structures.