Other

  • Notice distance for administrative discretionary permits300 ft

    Notice shall be mailed to all owners of real property within three hundred (300) feet of the subject property

  • Time to file an appeal10 days

    An appeal shall be filed ... within ten (10) calendar days

  • Time limit to commence use or construction2 years

    a permit or approval shall expire if the use or development authorized by the permit or approval is not commenced within two (2) years

  • Time limit to complete construction3 years

    construction is not completed within three (3) years

  • A Minor Conditional Use Permit may be approved for a limited term, not to exceed five (5) years

  • Notice shall be mailed to all owners of real property within five hundred (500) feet of the subject property

  • Design review shall not be required for single-family dwellings and accessory structures

  • Notice distance for drive-thru facilities and cemeteries1,000 ft

    Notice of a public hearing for a Conditional Use Permit for a drive-thru facility shall be mailed to all owners of real property within one thousand (1,000) feet

  • Maximum days of temporary use in 12 months180 days

    No temporary use shall be conducted on a site for more than one hundred eighty (180) days in any twelve (12) month period

  • Maximum duration of temporary use permit90 days

    A Temporary Use Permit shall be approved for a period not to exceed ninety (90) days

From the ordinance