Extracted standards
10 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Notice distance for administrative discretionary permits300 ft
Notice shall be mailed to all owners of real property within three hundred (300) feet of the subject property
- Time to file an appeal10 days
An appeal shall be filed ... within ten (10) calendar days
- Time limit to commence use or construction2 years
a permit or approval shall expire if the use or development authorized by the permit or approval is not commenced within two (2) years
- Time limit to complete construction3 years
construction is not completed within three (3) years
- Maximum term for minor conditional useConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. permit5 years
A Minor Conditional Use Permit may be approved for a limited term, not to exceed five (5) years
- Notice distance for discretionary actions requiring a public hearingConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote.500 ft
Notice shall be mailed to all owners of real property within five hundred (500) feet of the subject property
- Single-familySingle-family dwellingOne dwelling unit on its own lot, usually detached from its neighbours. dwellings exempt from design review
Design review shall not be required for single-family dwellings and accessory structures
- Notice distance for drive-thru facilities and cemeteries1,000 ft
Notice of a public hearing for a Conditional Use Permit for a drive-thru facility shall be mailed to all owners of real property within one thousand (1,000) feet
- Maximum days of temporary use in 12 months180 days
No temporary use shall be conducted on a site for more than one hundred eighty (180) days in any twelve (12) month period
- Maximum duration of temporary use permit90 days
A Temporary Use Permit shall be approved for a period not to exceed ninety (90) days
From the ordinance
This chapter establishes the overall structure for the application, review, and action on discretionary permits and legislative actions.