Other
- Extreme slope permit not required
Installation of renewable energy systems are permitted to be constructed on an extreme slope without the need for an extreme slope permit
- Maximum heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first. for ground-mounted systems12 ft
exceed 12 feet in height, as measured from existing grade
- SetbackSetbackThe distance a building must be held back from a lot line. encroachment prohibitedProhibitedNot allowed in the district at all, short of rezoning or a variance.
such systems do not encroach into a setback area
From the ordinance
Installation of renewable energy systems are permitted in any zoning district through a minor site plan review application, provided that such systems do not encroach into a setback area or exceed 12 feet in height...