Signal Hill, California · District

SP-19

SP-19 General Industrial Specific Plan
IndustrialGeneral IndustrialAll Signal Hill districts0

Dimensional standards

SP-19 lot requirementsSTREETSTREETbuildable areaFront 25 ftRear 20 ftSide 10 ftStreet side 5 ftMin width 100 ftMin depth 150 ftMIN LOT AREA20,000 sq ftMAX HEIGHT45 ft / 5 storiesMAX LOT COVERAGE50%
Plan view of the district’s stated lot requirements. Solid line: the property line. Dashed: the setback lines the ordinance imposes; a building must stay inside the tinted envelope. Drawn from the figures extracted below — illustrative, not a survey.

Uses

Extracted standards

17 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Height

Noise

  • Noise ambient levels

    Presumed ambient base noise levels: Residential night 50, day 60; Commercial night 60, day 65; Industrial N/A.

Other

  • The maximum height for fences, walls and hedges shall be as approved during the site plan and design review process.

  • Hardscape limited to driveways and walkways

    Hardscape in front and street side setbacks is limited to driveways and walkways only.

  • Minimum landscaping10 pct

    Minimum landscaping 10% of lot area

  • Overhead utilities allowed

    Overhead utility lines may remain overhead, provided the developer removes inactive utility service lines, rearranges existing lines, etc.

  • Signs conform to Chapter 20.58

    All signs shall conform to the number, location and size requirements of Chapter 20.58.

  • Transportation improvements for large development

    Nonresidential development comprising more than twenty-five thousand square feet of building area shall provide carpool and vanpool preferential parking spaces, bicycle racks, and transportation information displays.

  • Trash storage area

    A trash storage area shall be provided with bins or dumpsters of sufficient size and number to ensure containment of all solid waste materials.

  • Required yards landscaped

    All required yards shall be fully landscaped and automatically irrigated.

Parking

  • Parking requirement

    One parking space for each one thousand square feet of warehouse or manufacturing area within a building and one parking space for each two hundred and fifty square feet of office area within a building.

Setback

From the ordinance

Area 1 – Concrete batch plant. Maximum height 60 ft. Front setback 5 ft. Parking per 20.39.100.
20.39.030, 20.39.050, 20.39.060, 20.39.100

Parking requirements

{
  "office": "1 per 250 sq ft",