Placer County Unincorporated, California · General provision

Section 17.58.160

Extracted standards

7 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Approval time with EIR6 months

    If an environmental impact report is prepared... within six months

  • Approval time with negative declaration3 months

    If a negative declaration is adopted... the project shall be approved or disapproved within three months

  • Discontinuance lapse12 months

    ceases to operate for more than 12 consecutive months

  • Maximum extension per request3 years

    extend the expiration date ... by no more than a total of three years

  • Maximum total extension6 years

    for a total of no more than six years

  • Permit implementation validity36 months

    An approved permit is valid for 36 months from its effective date

  • Permit lapse if no time limit24 months

    within 24 months from the effective date of the approval

From the ordinance

If a negative declaration is adopted... the project shall be approved or disapproved within three months... If an environmental impact report is prepared... within six months... An approved permit is valid for 36 months from its effective date... within 24 months from the effective date of the approval... ceases to operate for more than 12 consecutive months... extend the expiration date ... by no more than a total of three years... for a total of no more than six years
Section 17.58.160