8 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Abandonment after idle

    A surface mining operation that remains idle for over one year without obtaining approval of an interim management plan shall be considered abandoned.

  • Annual inspection

    The community development department shall arrange for inspection of a surface mining operation within six months of receipt of the annual report. No more than one inspection per twelve-month period.

  • Annual report required

    The owner of a surface mining operation shall forward an annual report to the community development department and the supervisor of mine reclamation.

  • In addition to findings for the approval of conditional use permits (Section 21.19.050), approval for surface mining operations shall include a finding that the project complies with the provisions of state law and regulations.

  • Financial assurance required

    The applicant shall post security in the form of a corporate surety bond, trust fund, irrevocable letter of credit, or other method acceptable to the city.

  • Interim management plan required

    The operator of a surface mining operation that has been idle for over one year shall submit an interim management plan.

  • Minor revision limit10 pct

    Minor recontouring of final topography affecting no more than ten percent of the site.

  • Reclamation plan required

    The city shall require a reclamation plan for surface mining operations.

From the ordinance

Surface mining operations require a conditional use permit and reclamation plan approval.