Orange Cove, California · General provision

17.56.060.A

Extracted standards

4 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • New street dedication required

    If the development does not border or is not traversed by an existing street, the applicant may be required to: Dedicate all necessary rights-of-way for new streets to serve the development, including the ultimate width established by the city as the standard for such streets;

  • New street improvements required

    Install all improvements required by the city for new streets, including but not limited to curbs, gutters, sidewalks, street signs, street lights, street trees, drainage facilities, sewer facilities, water facilities, and traffic signals;

  • Street dedication required

    If the development borders or is traversed by an existing street, the applicant may be required to: Dedicate all necessary rights-of-way to widen a bordering minor or collector street to the extent of one-half or the ultimate width established by the city as the standard for such minor or collector street, or the full extent required for a frontage road;

  • Street improvements required

    Install curbs, gutters, sidewalks, street signs, street lights and street trees along the street or streets bordering or traversing the proposed development;

From the ordinance

If the development borders or is traversed by an existing street, the applicant may be required to: Dedicate all necessary rights-of-way to widen a bordering minor or collector street to the extent of one-half or the ultimate width established by the city as the standard for such minor or collector street, or the full extent required for a frontage road; ...
17.56.060.A