Orange County Unincorporated, California · General provision

Sec. 7-9-308

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Labor and material bond as percentage of estimated improvement cost100 pct

    one hundred (100) percent

  • Performance bond as percentage of estimated improvement cost100 pct

    one hundred (100) percent

From the ordinance

If bonds are furnished by one (1) of the authorized corporate sureties: (1) A performance bond in the amount of one hundred (100) percent of the estimated cost of the improvement. (2) A labor and material bond in the amount of one hundred (100) percent of the estimated cost of the improvement.
Sec. 7-9-308