Section 12.05.100

Extracted standards

6 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Construction completion time limit3 years

    construction shall be completed thereon within three (3) years from the effective date of the approval of such permit by the Planning Agency

  • Construction permit restriction before expiration60 days

    Construction permits, including grading permits, shall not be issued for projects that are within sixty (60) days of the expiration of the land use permit unless the applicant adequately demonstrates to the Planning Director that the project can satisfy the time limit provisions of this Chapter.

  • Soil condition requirement above 5,000 feet5,000 ft

    No use of property shall occur pursuant to a Development Permit approved under this Section nor Use Permit issued pursuant to this Chapter, nor shall any building permit be issued pursuant to any such Development Permit or Use Permit for any construction at an elevation above five thousand (5,000') feet until the Chief Building Inspector of the County of Nevada or his authorized agent determines that the soil conditions for the project site are adequate to accommodate construction activities.

  • Maximum extension of time2 years

    No more than two-year (2) extensions of time may be granted.

  • Mining use permit expiration5 years

    For mining Use Permits, the permit shall specify a time limit specific to the operation. If no such time limit is specified, the permit shall expire after five (5) years.

  • Maximum time for phased projects7 years

    Time limits for completion of construction shall be established by the permit conditions, but in no case shall exceed seven (7) years from the date of land use permit approval.

From the ordinance

Whenever the use of land, including but not limited to use of or right to construct any structure, is authorized, pursuant to any permit (including but not limited to Development Permits, and Use Permits, but not variances) in accordance with this Chapter, construction shall be completed thereon within three (3) years from the effective date of the approval of such permit by the Planning Agency; otherwise, the permit shall become null and void as to any portion of the use not completed unless an extension of time is granted pursuant to this Section.