Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Completion threshold for nonconformingNonconformingLawful when built, but not compliant with the rules now in force; usually allowed to continue but not to expand. projects10 percent
All nonconforming projects that are at least ten (10) percent completed in terms of the total expected cost may be completed.
- Construction start before effective date180 days
All nonconforming projects on which construction was begun at least one hundred eighty (180) days before the effective date may be completed.
From the ordinance
All nonconforming projects on which construction was begun at least one hundred eighty (180) days before the effective date, as well as all nonconforming projects that are at least ten (10) percent completed may be completed in accordance with the terms of their permits.