Lighting

  • No illumination unless required

    No facility may be illuminated unless specifically required by the Federal Aviation Administration or other government agency. Beacon lights are not permitted unless required by the Federal Aviation Administration or other government agency. Any required lighting shall be shielded to eliminate, to the maximum extent possible, impacts on the surrounding neighborhoods.

Noise

  • Backup generator operation restrictions

    Backup generators shall only be operated during periods of power outages, and shall not be tested on weekends or holidays, or between the hours of 7:00 p.m. and 7:00 a.m.

Other

  • Antenna flush mounted

    Antenna elements shall be flush mounted, if feasible.

  • As-built drawings within 90 days90 days

    The permittee shall submit an as built drawing within 90 days after installation of the facility. As-built drawings shall be in an electronic format acceptable to the City which can be linked to the City's GIS.

  • Assignment notice at least 90 days prior90 days

    The permittee shall notify the City in writing at least 90 days prior to any transfer or assignment of the permit. The written notice required in this Section must include: (i) the transferee's legal name; (ii) the transferee's full contact information, including a primary contact person, mailing address, telephone number and email address; and (iii) a statement signed by the transferee that the transferee shall accept all permit terms and conditions.

  • Cabinet removal within 90 days90 days

    Should the utility company servicing the facility with electrical service that does not require the use of an above ground meter cabinet, the permittee shall at its sole cost and expense remove the meter cabinet and any related foundation 90 days of such service being offered and reasonably restore the area to its prior condition.

  • Collocation design

    All antenna mounts shall be designed so as not to preclude possible future collocation by the same or other operators or carriers.

  • Construction start within one year12 months

    The installation and construction approved by a wireless telecommunications facility permit shall begin within one year after its approval or it will expire without further action by the City.

  • Contact information update within 30 days30 days

    The permittee shall submit and maintain current at all times basic contact and site information on a form to be supplied by the City. The permittee shall notify the City of any changes to the information submitted within 30 days of any change, including change of the name or legal status of the owner or operator.

  • Findings required for discretionary permit

    No discretionary permit shall be granted for a wireless telecommunications facility unless the approving party makes all of the following findings: 1. All notices required for the proposed installation have been given. 2. The proposed facility would comply with all applicable laws. 3. The applicant has provided sufficient evidence supporting the applicant's claim that it has the right to enter the public right-of-way pursuant to State or Federal law, or the applicant has entered into an agreement with the City permitting the applicant to use the public right-of-way. 4. The applicant has demonstrated one of the following: (a) the design and location for the proposed installation will be minimally intrusive on the purposes of this Section 17.400.177; or (b) denial of the proposed facility would 'effectively prohibit' the deployment of wireless facilities in violation of Federal law.

  • Permittee assumes full liability

    The permittee shall assume full liability for damage or injury caused to any property or person by the facility.

  • Hold harmless

    Additionally, to the fullest extent permitted by law, the permittee, and every permittee and person in a shared permit, jointly and severally, shall defend, indemnify, protect and hold the City and its elected and appointed Council members, boards, commissions, officers, officials, agents, consultants, employees and volunteers harmless from and against all claims, suits, demands, actions, losses, liabilities, judgments, settlements, costs (including, but not limited to, attorney's fees, interest and expert witness fees), or damages claimed by third parties against the City for any injury claim, and for property damage sustained by any person, arising out of, resulting from, or are in any way related to the wireless telecommunications facility, or to any work done by or use of the public right-of-way by the permittee, owner or operator of the wireless telecommunications facility, or their agents, excepting only liability arising out of the sole negligence or willful misconduct of the City and its elected and appointed Council members, boards, commissions, officers, officials, agents, consultants, employees and volunteers.

  • Indemnification

    Permittee shall defend, indemnify, protect and hold harmless the City, its elected and appointed Council members, boards, commissions, officers, officials, agents, consultants, employees, and volunteers from and against any and all claims, actions, or proceeding against the City, and its elected and appointed Council members, boards, commissions, officers, officials, agents, consultants, employees, and volunteers to attack, set aside, void or annul, an approval of the City, Planning Commission or City Council concerning this permit and the project.

  • Insurance required

    The permittee shall obtain, pay for and maintain, in full force and effect until the facility approved by the permit is removed in its entirety from the public right-of-way, an insurance policy or policies meeting the City of Westminster's insurance requirements for contractors to perform work with public right-of-way.

  • When accessory equipment will be ground-mounted, such accessory equipment shall be enclosed within a structure that does not exceed a height of 5 feet, not exceed a footprint of 15 square feet, and shall be fully screened and/or camouflaged with landscaping and/or architectural treatment.

  • When accessory equipment will be ground-mounted, such accessory equipment shall be enclosed within a structure that does not exceed a height of 5 feet, not exceed a footprint of 15 square feet, and shall be fully screened and/or camouflaged with landscaping and/or architectural treatment.

  • Maximum pole mounted equipment volume

    Pole mounted equipment and enclosure, exclusive of antennas, shall not exceed total volume allowed by City's design standards.

  • Maximum strand mounted equipment volume2 cubic ft

    Strand mounted equipment and enclosure shall not exceed 2 cubic feet in total volume.

  • All ground-mounted facility, pole-mounted equipment, or walls, fences, landscaping or other screening methods shall be installed at least 18 inches from the curb and gutter flow line.

  • No installation in tree drip line

    No facility shall be permitted to be installed in the drip line of any tree in the right-of-way unless the facility is to be collocated on an existing facility in the drip line.

  • No interference with existing structures without consent

    The permittee shall not move, alter, temporarily relocate, change, or interfere with any existing structure, improvement or property without the prior consent of the owner of that structure, improvement or property. No structure, improvement or property owned by the City shall be moved to accommodate a wireless telecommunications facility unless the City determines that such movement will not adversely affect the City or any surrounding businesses or residents, and the permittee pays all costs and expenses related to the relocation of the City's structure, improvement or property.

  • No interference with public safety facilities

    A facility shall not interfere with access to a fire hydrant, fire station, fire escape, water valve, underground vault, valve housing structure, or any other public health or safety facility.

  • No obstruction to pedestrian or vehicular traffic

    Each component part of a facility shall be located so as not to cause any physical or visual obstruction to pedestrian or vehicular traffic, incommode the public's use of the right-of-way, or safety hazards to pedestrians and motorists.

  • No permit transfer before construction completion

    The permittee shall not transfer the permit to any person prior to the completion of the construction of the facility covered by the permit, unless and until the transferee of the permit has submitted the security instrument.

  • In locations where homes are only along one side of a street, above-ground accessory equipment shall not be installed directly in front of a residence. Such above-ground accessory equipment shall be installed along the side of street with no homes.

  • Relocation requirements

    The permittee shall modify, remove, or relocate its facility, or portion thereof, without cost or expense to City, if and when made necessary by: (i) any public improvement project, including, but not limited to, the construction, maintenance, or operation of any underground or above ground facilities, including, but not limited to, sewers, storm drains, conduits, gas, water, electric or other utility systems, or pipes owned by City or any other public agency; (ii) any abandonment of any street, sidewalk or other public facility; (iii) any change of grade, alignment or width of any street, sidewalk or other public facility; or (iv) a determination by the Director that the wireless telecommunications facility has become incompatible with public health, safety or welfare or the public's use of the public right-of-way. Such modification, removal, or relocation of the facility shall be completed within 90 days of notification by City unless exigencies dictate a shorter period for removal or relocation.

  • Repair obligations

    The permittee shall repair, at its sole cost and expense, any damage, including, but not limited to, subsidence, cracking, erosion, collapse, weakening, or loss of lateral support to City streets, sidewalks, walks, curbs, gutters, trees, parkways, street lights, traffic signals, improvements of any kind or nature, or utility lines and systems, underground utility line and systems, or sewer systems and sewer lines that result from any activities performed in connection with the installation and/or maintenance of a wireless telecommunications facility in the public right-of-way.

  • Required notices and signs posted

    At all times, all required notices and/or signs shall be posted on the site as required by the Federal Communications Commission, California Public Utilities Commission, any applicable licenses or laws, and as approved by the City. The location and dimensions of a sign bearing the emergency contact name and telephone number shall be posted pursuant to the approved plans.

  • Right-of-way agreement required

    Prior to the issuance of any encroachment permit, permittee shall be required to enter into a right-of-way agreement with the City in accordance with the City's past practice.

  • Security design to prevent unauthorized access

    Each facility shall be designed to be resistant to, and minimize opportunities for, unauthorized access, climbing, vandalism, graffiti and other conditions that would result in hazardous situations, visual blight or attractive nuisances. For any discretionary permit, the Director may require the provision of warning signs, fencing, anti-climbing devices, or other techniques to prevent unauthorized access and vandalism when, because of their location and/or accessibility, a facility has the potential to become an attractive nuisance. Additionally, no lethal devices or elements shall be installed as a security device.

  • Subdued colors and non-reflective materials

    All facilities shall have subdued colors and non-reflective materials that blend with the materials and colors of the surrounding area and structures.

  • Traffic safety compliance

    Facilities shall be designed consistent with all applicable safety standards and shall be installed only in a location which does not violate pedestrian or traffic safety standards.

  • Wind load engineering

    Each facility shall be properly engineered to withstand wind loads as required by this Code or any duly adopted or incorporated code.

  • Written consent to conditions within 30 days30 days

    Permittee shall agree in writing that the permittee is aware of, and agrees to abide by, all conditions of approval imposed by the wireless telecommunications facility permit within 30 days of permit issuance. The permit shall be void and of no force or effect unless such written consent is received by the City within said 30-day period.

Signage

  • No signs or advertising

    No facility shall bear any signs or advertising devices other than certification, warning or other signage required by law or permitted by the City.

From the ordinance

All facilities shall have subdued colors and non-reflective materials that blend with the materials and colors of the surrounding area and structures.