Extracted standards
1 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Undergrounding required
All utility lines underground for new construction/relocation/change to nonresidential
From the ordinance
In connection with the new construction or relocation of a main building, or a change of use to a nonresidential use, all utility lines within the site boundaries shall be placed underground. Necessary surface-mounted utility equipment is permitted provided it is screened from public view in the same manner as required for mechanical equipment as provided in section 99.09.02.