18.108.025 and 18.108.026
Extracted standards
3 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Construction fencing to protect stream setbacksSetbackThe distance a building must be held back from a lot line. and wetlands
Where appropriate, the director may require an applicant to install and maintain construction fencing, or other means of demarcation acceptable to the director, in a manner that protects stream setback areas, wetlands, wildlife corridors, sensitive areas and other protected features from intrusion or disturbance during land clearing and earth-disturbing activities.
- Minimum stream setbackSetbackThe distance a building must be held back from a lot line.35 ft
Ephemeral or intermittent streams that do not meet the criteria for a stream as defined in Section 18.108.030 shall have a minimum 35-foot setback.
- Minimum wetland setbackSetbackThe distance a building must be held back from a lot line.50 ft
Construction of main or accessory structures, earthmoving activity, land clearing or agricultural uses of land as defined by Section 18.08.040 shall be set back 50 feet from the delineated wetland boundary.
From the ordinance
Ephemeral or intermittent streams that do not meet the criteria for a stream as defined in Section 18.108.030 shall have a minimum 35-foot setback.