Monterey County Unincorporated, California · General provision

21.64.070

Extracted standards

6 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Construction must start within 60 days60 days

    Actual construction on the permanent residence must start within sixty (60) days of the issuance of the building permit for the residence or the use of the temporary residence must cease.

  • Building permit for permanent residence required

    The use of the temporary residence may not begin until a building permit for the permanent residence is issued.

  • Maximum duration of temporary residence18 months

    The use of the temporary residence must cease within eighteen (18) months of the date of issuance of the building permit for the permanent residence or occupancy of the permanent dwelling whichever occurs first.

  • No temporary residence if other residences exist

    No temporary residence may be allowed if other residences exist on the lot.

  • Temporary residences per lot1 unit

    Only one temporary residence may be allowed on a lot.

  • Water and sewage disposal required

    The temporary residence must be connected to a water source and sewage disposal facility approved by the Director of Environmental Health.

From the ordinance

Recreational vehicles or mobilehomes may be used as a temporary residence during the course of actual construction of a single family dwelling subject to the following standards: Only one temporary residence may be allowed on a lot. No temporary residence may be allowed if other residences exist on the lot.
21.64.070