Other

  • Large collection facility use permit

    Large collection facility requires a use permit.

  • Processing facility use permit

    Processing facility requires a use permit in C-2, I, or IP zones.

  • Small collection facility approval

    Small collection facility requires approval from Planning Director.

From the ordinance

A small collection facility may be permitted in any C, I, IP, or RCO zone and in an R zone when the site is the location of an appropriate non-profit agency... A large collection facility may be permitted in any zone after first securing a use permit. A processing facility may be permitted in a C-2, I, or IP use zone after first securing a use permit.