Grading
- GradingGrading (cut & fill)Reshaping land by removing earth (cut) or adding it (fill), often capped by volume. plan required
All grading must be completed in accordance with Document No. 35123. Regrading not permitted except per revised plan. Earth slopes natural appearance.
Other
- Maximum peak soil velocity0.4 in/sec
Explosive charges limited to peak soil velocity level of 0.4 inches per second.
- Minimum driveway length20 ft
Minimum length of driveway between property line and garage entrance shall not be less than 20 feet.
- Minimum separation from adjoining residence20 ft
In no case shall a home be sited within twenty feet of an adjoining residence.
The side setback on the opposite side of the dwelling shall be no less than fifteen feet.
- Street surface during construction
All roads used in connection with construction shall be surfaced with all weather surfacing material prior to the framing stage.
- Water supply and hydrants required
Water supply and fire hydrants sufficient for fire fighting purposes shall be available before building materials are transported to any building site.
From the ordinance
The required front setback shall be reduced to fifteen feet. The required side setback from one side lot line may be reduced to a minimum of five feet for any dwelling. The side setback on the opposite side of the dwelling shall be no less than fifteen feet.