Extracted standards
5 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Front yardYardThe open space left between a building and its lot line — the space a setback creates. prohibitedProhibitedNot allowed in the district at all, short of rezoning or a variance.
Temporary structures are prohibited in front yards
- Maximum duration179 days
Temporary structures are those that are erected for 179 days or less
- Minimum setbackSetbackThe distance a building must be held back from a lot line. from property line20 ft
must be 20 feet from any rear or side property lines
Signage
- Maximum sign area22 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
Any temporary or permanent signage advertising any temporary special event shall be a maximum of 22 square feet
- Maximum sign heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first.8 ft
and a maximum height of eight feet
From the ordinance
Any temporary or permanent signage advertising any temporary special event shall be a maximum of 22 square feet and a maximum height of eight feet; and The installation of temporary structures, such as tents and stages, is permissible in connection with an approved Temporary Special Events Conditional Use Permit, subject to all applicable laws and regulations and the following: (a) Temporary structures are those that are erected for 179 days or less; (b) Temporary structures are prohibited in front yards and must be 20 feet from any rear or side property lines;