Other
- Extension decision deadline30 days
The zoning administrator shall acknowledge the request and shall make a decision regarding the requested extension within 30 days after receipt of the request.
- Extension request deadline before expiration90 days
A single-year extension may be given upon written request by the applicant to the zoning administrator made within 90 days before the expiration of the approved site plan.
- Time to file final site plan after preliminary approval3 months
The applicant shall have not more than three months after receiving official notification concerning the preliminary site plan to file a final site plan
- Site plan approval expiration1 year
Approval of a site plan submitted under the provisions of this article shall expire one year after the date of such approval unless building permits have been obtained
From the ordinance
Approval of a site plan submitted under the provisions of this article shall expire one year after the date of such approval unless building permits have been obtained... The applicant shall have not more than three months after receiving official notification concerning the preliminary site plan to file a final site plan...