South Hill, Virginia · General provision

Sec. 94.1-125

Extracted standards

9 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Letter of intent to annex required

    A letter of intent to annex the house to the land must be submitted with the application.

  • Masonry foundation completion time60 days

    A masonry foundation is preferred and it shall be completed within 60 days after issuance of certificate of occupancy.

  • The occupant must own the land.

  • Roof must be shingled and pitched

    The roof is to be shingled and pitched.

  • Siding material approval required

    Any siding material other than vertical metal shall require approval by the building official.

  • Steps and landings required

    Front and/or rear steps and landings shall be provided as required to meet state law.

  • Title must be returned to DMV

    The title shall be returned to the Division of Motor Vehicles.

  • Underskirting required

    Underskirting continued to ground shall be installed and it shall be of the same material as the siding or compatible thereto.

  • Wheels and tongue must be removed

    The wheels and tongue must be removed.

From the ordinance

The installation of double-wide or multiunit manufactured housing must comply with the following: ... The wheels and tongue must be removed. ... Underskirting continued to ground shall be installed ... A masonry foundation is preferred and it shall be completed within 60 days after issuance of certificate of occupancy. ... The roof is to be shingled and pitched. ... Any siding material other than vertical metal shall require approval by the building official.
Sec. 94.1-125