Extracted standards
6 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Antenna size limits on existing light poles
The antenna does not exceed 30 inches in height or 12 inches in diameter. No portion of the antenna may extend beyond 18 inches from the side of the pole.
- Maximum heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first. relative to by-rightBy rightPermitted outright: if the plans meet the written rules, permission cannot be withheld. principal use
The maximum height of a small cell facility, including antenna, shall not exceed the maximum permitted height of a by-right principal use of the underlying zoning district.
- Minimum lot size for small cell facilities on nonresidential buildings43,560 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
Within all permitted zoning districts, a minimum lot size of one acre is required.
- Removal within days after no longer in use120 days
All antennas and related equipment, to include ground-mounted equipment, must be removed within 120 days after such antennas or related equipment are no longer in use.
- SetbackSetbackThe distance a building must be held back from a lot line. compliance with underlying districtZoning districtA mapped area with one set of rules, identified by a code like R-1 or B-2.
Small cell facilities, including ground-mounted equipment, must comply with the minimum setback provisions of the underlying zoning district.
- Wiring, cables, and conduit enclosed
All antennae, wiring, cables, and conduits must be contained in a fully enclosed structure, screened or camouflaged.
From the ordinance
Small cell facilities on utility or light poles... Small cell facilities on nonresidential buildings or structures... minimum lot size of one acre... maximum height... removal within 120 days...