Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Grading
- Minimum gradingGrading (cut & fill)Reshaping land by removing earth (cut) or adding it (fill), often capped by volume. depth requiring plan18 inches
A depth of grading or re-grading of 18 inches or more.
- Minimum site area requiring gradingGrading (cut & fill)Reshaping land by removing earth (cut) or adding it (fill), often capped by volume. plan5,000 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
A site area of 5,000 square feet or greater.
From the ordinance
A site grading plan shall be submitted for any of the following: (2) A site area of 5,000 square feet or greater. (3) A depth of grading or re-grading of 18 inches or more.