Prince William County Unincorporated, Virginia · General provision
Sec. 32-210.01.5(d)
Extracted standards
1 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Portable storage unit construction duration180 days
Up to 180 days or until final inspection, whichever is shorter.
From the ordinance
In the case of a portable storage unit or units located on the lot for the purpose of storing construction materials... the portable storage unit or units may be permitted, with an approved temporary activity permit, on the property for up to 180 days or until a final inspection has been completed by the County, whichever is shorter.