Extracted standards
1 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Floodplain
- Days to start construction after permit180 days
Start of construction... means the date the building permit was issued, provided the actual start of construction... was within one hundred eighty (180) days of the permit date.
From the ordinance
Start of construction... means the date the building permit was issued, provided the actual start of construction... was within one hundred eighty (180) days of the permit date.