Northampton County Unincorporated, Virginia · General provision

§154.2.040-041

Extracted standards

3 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Certificate of occupancy required

    No change in the use or occupancy of any existing building (except for an existing single-family dwelling) may be made, nor may any new building or dwelling be occupied for any purpose until a certificate of occupancy has been issued.

  • Zoning clearance approval time30 days

    Within 30 days of receipt of the application, the Zoning Administrator shall approve or disapprove the application.

  • Zoning clearance required

    It shall be unlawful to change the use of land or structures or to alter or erect structures until a zoning clearance is approved.

From the ordinance

It shall be unlawful to change the use of land or structures or to alter or erect structures until a zoning clearance is approved... No change in the use or occupancy of any existing building (except for an existing single-family dwelling) may be made... until a certificate of occupancy has been issued.
§154.2.040-041