Dimensional standards
Extracted standards
6 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Front driveway/parking must be paved
Any driveway or parking area located in front of the dwelling must be paved with an asphalt or concrete surface.
- Maintenance easement required
A maintenance easement must be established for every lot in a zero-lot-line development.
- Maximum front yardYardThe open space left between a building and its lot line — the space a setback creates. driveway/parking coverage35 pct
Any driveway or parking area located in the front yard shall cover no more than 35 percent of the front yard area.
- Maximum garage door width9 ft
Garage doors are limited to no greater than nine feet in width.
- Maximum front-loaded garage width14 ft
and no greater than 14 feet
- Maximum front-loaded garage width as percentage of lot widthLot widthHow wide a lot must be, usually measured at the front setback line.35 pct
Front loaded garage structures are limited in width to no greater than 35 percent of the lot width
From the ordinance
For any zero-lot-line condition, the following additional standards and limitations shall apply: (1) Front loaded garage structures are limited in width to no greater than 35 percent of the lot width, and no greater than 14 feet. Garage doors are limited to no greater than nine feet in width. (2) Any driveway or parking area located in front of the dwelling must be paved with an asphalt or concrete surface. (3) Any driveway or parking area located in the front yard shall cover no more than 35 percent of the front yard area.