Martinsville, Virginia · General provision

Section I. Bonding and construction permits

Extracted standards

5 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • located within five (5) feet of any required setback

  • Issuance of a land disturbance permit (for projects with greater than five thousand (5,000) square feet of disturbed land area).

  • Maintenance bond percentage10 pct

    in no instance shall be less than ten (10) percent of the total construction cost of the improvements subject to the bond.

  • Maintenance bond period2 years

    The maintenance bond may be released at the end of two (2) years from the date of city acceptance of responsibility.

  • Minimum bond period12 months

    The period of the initial bond (surety) agreement shall be not less than twelve (12) months from its effective date.

From the ordinance

The period of the initial bond (surety) agreement shall be not less than twelve (12) months... maintenance bond ... less than ten (10) percent... land disturbance permit (for projects with greater than five thousand (5,000) square feet... located within five (5) feet of any required setback
Section I. Bonding and construction permits