Dimensional standards
Lot
Extracted standards
7 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Building permit required
A building permit is required from the county and a copy has to be filed with the town within ten business days of the placement of the use on the site.
- Duration until occupancy
The use is permitted until the issuance of the last occupancy permit is approved for the development and until the completion of any bonded public improvements.
- Location requirements
The use shall be located on a lot that is within a recorded subdivision or on a lot with an approved site plan or a lot with an approved building location zoning.
- Minimum distance from property line20 ft
The use shall not be located closer than 20 feet from the property line of the lot upon which it is located.
- Zoning administrator review
The zoning administrator shall review and approve or deny a request for temporary construction and/or sales trailer permit.
- Zoning permit required
A zoning permit shall be obtained for the use at least ten business days prior to the time it is placed on the property.
Parking
- Parking spaces2 spaces
The use shall provide two off-street parking spaces on the lot or land on which the use is located.
From the ordinance
A minimum lot area of 2,000 square feet shall be provided for this use. The use shall not be located closer than 20 feet from the property line of the lot upon which it is located.