Dimensional standards
Extracted standards
6 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Duration
The use is permitted until the issuance of the last occupancy permit is approved for the development and until the completion of any bonded public improvements.
- Location requirement
The use shall be located on a lot that is within a recorded subdivision or on a lot with an approved site plan or a lot with an approved building location zoning.
- Minimum lot areaMinimum lot areaThe smallest parcel on which the district allows anything to be built.2,000 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
A minimum lot area of 2,000 square feet shall be provided for this use.
- Parking spaces2 spaces
The use shall provide two off-street parking spaces on the lot or land on which the use is located. These parking spaces shall include the required handicapped space.
- SetbackSetbackThe distance a building must be held back from a lot line. from property line20 ft
The use shall not be located closer than 20 feet from the property line of the lot upon which it is located.
- Zoning permit
A zoning permit shall be obtained for the use at least ten business days prior to the time it is placed on the property.
From the ordinance
Construction and/or sales trailers are permitted subject to the following provisions: