10.11.01
Extracted standards
7 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Limitation after denial or withdrawal12 months
No new application substantially the same as one denied or withdrawn will be accepted for review within 12 months of the date of such denial or withdrawal.
- Extension request notice30 days
A written request for extension must be submitted to the Zoning Administrator at least 30 days before the expiration date.
- Minor change building addition limit5 pct
Minor additions to principal buildings and corresponding additions to parking areas, provided the cumulative total of all building additions neither exceed 5% of the existing gross floor area nor exceed maximum permitted floor area ratio.
- Agency review time25 business days
The Zoning Administrator will request agencies to review and provide written comments within 25 business days.
- Subsequent review time20 business days
Subsequent reviews will be completed within 20 business days.
- Period of validity5 years
Special Exceptions are valid for a period of up to 5 years from the date of approval unless the approval specifies an alternate period of validity.
- Work session scheduling100 days
The work session will be scheduled within 100 days following the public hearing, or such longer time as agreed by the applicant.
From the ordinance
To provide the Board of Supervisors with an opportunity for discretionary review of requests to establish or construct uses or structures that have the potential for a deleterious impact upon the health, safety, and welfare of the public.