Loudoun County Unincorporated, Virginia · General provision

Section 4.07.09

Dimensional standards

lot requirementsSTREETMIN LOT AREA1 ac
Plan view of the district’s stated lot requirements. Solid line: the property line. Dashed: the setback lines the ordinance imposes; a building must stay inside the tinted envelope. Drawn from the figures extracted below — illustrative, not a survey.

Uses

Permitted by right1

Conditional / special use1

  • utility substations requiring special exception in AR Cluster Subdivisions

Extracted standards

3 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Required buffer type

    All Utility Substations and accessory storage yards require a minimum Buffer Type C...

  • Commission Permit required

    A Commission Permit (10.09) is required for a Utility Substation unless the Utility Substation is specifically delineated in the Comprehensive Plan.

  • Private road access allowed

    Utility Substations may be accessed by a private road.

From the ordinance

The minimum lot size of a Utility Substation is 1 acre exclusive of major floodplain. ... Utility Substations must be set back a minimum of 100 feet from adjacent property with existing residential development...
Section 4.07.09