Loudoun County Unincorporated, Virginia · General provision

Section 3.04.F

Uses

Extracted standards

3 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Removal within 90 days of cessation of emergency90 days

    The temporary Fire and/or Rescue Station must be removed within 90 days of cessation of the Emergency event;

  • Removal within 90 days of completion of permanent station90 days

    The temporary Fire and/or Rescue Station must be removed within 90 days of completion of construction of the permanent Fire and/or Rescue Station.

Setback

  • Minimum setbackSetbackThe distance a building must be held back from a lot line. from lot line for temporary fire/rescue station15 ft

    All new structures associated with the Temporary Fire and/or Rescue Station must be set back a minimum of 15 feet from any lot line, or the minimum yard or setback of the underlying Zoning District, whichever is less restrictive.

From the ordinance

The erection of a new structure and/or occupancy of a legally existing structure for a temporary Fire and/or Rescue Station is permitted under the following Emergency events: ...
Section 3.04.F