Extracted standards
4 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Bond required
A cash or other bond may be required to cover the cost of removal and disposal of a temporary building when the conditional use permit expires.
- Conditional useConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. permit required
Portable buildings, except those specifically exempted below, may be located on a lot only upon the issuance of a conditional use permit, in accordance with § 420-1.11.
- Exemptions
In all residential districts, portable buildings may be used as accessory structures, the use of which is incidental to and used only in conjunction with the primary structure. Contractor's temporary office and storage sheds incidental to a construction project. Temporary restroom facilities.
- Temporary use
Such a building is for temporary use only and must be replaced with a permanent building or removed within two years. One extension may be requested and approved for not more than one additional year.
From the ordinance
Portable buildings, except those specifically exempted below, may be located on a lot only upon the issuance of a conditional use permit, in accordance with § 420-1.11.