  • Planning Commission decision time60 days

    Following the close of the public hearing, and within sixty (60) days of acceptance of a complete application, the Planning Commission shall forward its finding to the Town Council

From the ordinance

Following the close of the public hearing, and within sixty (60) days of acceptance of a complete application, the Planning Commission shall forward its finding to the Town Council, indicating their (Planning Commission) approval or disapproval of the proposed project, along with written reasons for its decision. Failure of the Planning Commission to take action within the required 60-day period shall be deemed approval of the project, unless the Town Council grants an extension of the timeframe.