Sec. 5-5007.D
Uses
Conditional / special use1
Extracted standards
7 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Abandonment period24 months
Any antenna or tower that is not operated for a continuous period of twenty-four (24) months shall be considered abandoned
- Landscaping buffer width4 ft
The standard buffer shall consist of a landscaped strip at least four (4) feet wide outside the perimeter of the facilities.
- Removal time after notice90 days
the owner of each such antenna or tower shall remove same within ninety (90) days of receipt of notice
- Security fence heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first.6 ft
Towers shall be enclosed by security fencing not less than six (6) feet in height
- SetbackSetbackThe distance a building must be held back from a lot line. from property line (1 ft per ft heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first.)
A setback of one (1) foot horizontally for each foot in height shall be provided from the base of the tower structure to any adjoining property line
- SetbackSetbackThe distance a building must be held back from a lot line. from off-site residential structure400 ft
The tower must be set back from any off-site residential structure no less than four hundred (400) feet.
- Tree removal limit200 ft
Existing trees within the lesser of two hundred (200) feet or the area controlled by the applicant/owner shall not be removed
From the ordinance
The purpose of this section is to establish general guidelines for the siting of towers and antennas. ...