Henrico County Unincorporated, Virginia · General provision

Sec. 24-2305.C.6.b

Extracted standards

1 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Planned development decision within 12 months12 months

    must not exceed 12 months from the date of acceptance of the completed application

From the ordinance

An application for planned development must be acted upon and a decision made within a reasonable time, which must not exceed 12 months from the date of acceptance of the completed application, unless the application is withdrawn or the applicant requests or consents to action beyond such period.
Sec. 24-2305.C.6.b