Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Major site plan required when
land disturbance >= 2,500 sq ft OR increase of gross floor area >= 1,000 sq ft OR outside agency review required
- Minor site plan required when
land disturbance < 2,500 sq ft AND increase of gross floor area < 1,000 sq ft AND no outside agency review
From the ordinance
Site plan, major: A major site plan is a required submission for development where the land disturbance will be 2,500 square feet or greater, increase of gross floor area is 1,000 square feet or more, or outside agency review is required... Site plan, minor: ... land disturbance will be less than 2,500 square feet, increase of gross floor area is below 1,000 square feet, no outside agency review is required...