Extracted standards
5 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Maximum new equipment cabinets without substantial change4 cabinets
Installation of more than standard number of new cabinets, but not to exceed 4, is substantial.
- Substantial change heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first. threshold (outside ROW)20 ft
For towers outside public rights-of-way, increase of more than 20 feet or 10% (whichever greater) is substantial.
- Substantial change heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first. threshold (in ROW)10 ft
For towers in rights-of-way and all wireless facilities, increase of more than 10% or 10 feet (whichever greater) is substantial.
- Substantial change protrusion threshold (outside ROW)20 ft
Protrusion from edge of tower more than 20 feet or width of tower at appurtenance level (whichever greater) is substantial.
- Substantial change protrusion threshold (in ROW)6 ft
Protrusion from edge of support structure more than 6 feet is substantial.
From the ordinance
The permissions granted by the Spectrum Act Section 6409 Wireless Facilities Deployment (Section 6409) shall be applicable only to wireless telecommunications facilities deemed to be an eligible facility in existence prior to the original enactment of this article. Modifications shall not substantially change eligible facilities.