Halifax County Unincorporated, Virginia · General provision

Sec. 53-155

Dimensional standards

Uses

Extracted standards

27 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Fencing & walls

Landscaping & trees

Other

  • Minimum distance from airport1 mi

    Large scale solar energy facilities shall not be located within one mile of an airport unless ...

  • Community meeting required

    A public meeting shall be held prior to the public hearing with the planning commission

  • Decommissioning plan update frequency5 years

    the update shall be no more frequently than once every five years and no less frequently than once every ten years.

  • Decommissioning plan update maximum frequency10 years

    the update shall be no more frequently than once every five years and no less frequently than once every ten years.

  • Glint and glare study required

    A glint and glare study that demonstrates either that the panels will be sited, designed, and installed to eliminate glint and glare effects ...

  • Maximum density of community/shared solar in 5-mile radius0.5 pct

    no more than one-half percent of the land in a five-mile radius of the center of any proposed new community/shared solar energy facility may be approved

  • Maximum density of large scale solar in 5-mile radius3 pct

    no more than three percent of the land in a five-mile radius of the center of any proposed new large scale solar energy facility may be approved

  • Ground-mounted solar energy generation facilities shall not exceed a height of 20 feet

  • Increased setbacks up to 800 feet and additional buffering may be included in the conditions for a particular permit on a case by case basis.

  • No construction on Sunday

    There shall be no construction operations on Sunday, except in the case of an emergency.

  • Prime farmland preservation10 pct

    If no more than ten percent of the site is prime farmland, this consideration will be waived

  • The project area shall be set back a distance of at least 150 feet from all public rights-of-way and main buildings on adjoining parcels

  • and a distance of at least 150 feet from adjacent property lines.

  • The project area shall be set back a distance of at least 150 feet from all public rights-of-way and main buildings on adjoining parcels

  • Site plan performance bond per megawatt100,000 dollars

    The amount of the site plan performance bond shall be $100,000.00 per megawatt.

  • Soil testing frequency5 years

    Testing shall be conducted prior to the issuance of a land disturbance permit and every five years thereafter.

  • Testing shall be conducted in no less than three locations for each 100 acres of project area.

  • Water testing frequency (initial)1 years

    The owner or operator shall test annually for the first five years after commercial operation commences

  • Water testing frequency (subsequent)3 years

    and every three years thereafter.

  • There shall be one well for each 100 acres of project area.

From the ordinance

A conditional use permit is required for each large scale and community/shared solar energy facility proposed to be constructed, installed, or operated in the county.
Sec. 53-155