  • Decommissioning period365 days

    Within 365 days of the date of abandonment, whether as declared by the county under subsection (b) or as scheduled by the owners or operator under subsection (c), the facility owner, site owner, or operator shall complete the physical removal of the solar energy facility in compliance with decommissioning plan established for such facility.

From the ordinance

Within 365 days of the date of abandonment, whether as declared by the county under subsection (b) or as scheduled by the owners or operator under subsection (c), the facility owner, site owner, or operator shall complete the physical removal of the solar energy facility in compliance with decommissioning plan established for such facility.