Goochland County Unincorporated, Virginia · General provision

Sec. 15-289.C

Dimensional standards

Extracted standards

4 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Abandonment period6 months

    A solar facility, or any portion thereof, shall be considered abandoned when not utilized for the generation of electricity for a continuous period of six months.

  • not exceed a height of 25 feet

  • Maximum noise level60 dBA

    Noise generated by the facility cannot exceed the lesser of that permitted for the district or 60 dBA

  • Maximum roof-mounted solar extension6 ft

    in no case extend more than six feet above the building's roof or parapet

From the ordinance

Ground-mounted facilities must be located no closer to a road than the principal building or use, meet all other principal building setbacks, and not exceed a height of 25 feet.
Sec. 15-289.C