  • Permit duration12 months

    issued for a 12-month period

  • Removal after certificate of occupancy30 days

    Mobile home must be removed 30 days from issuance of the certificate of occupancy for the permanent dwelling.

  • Renewal duration12 months

    The zoning administrator may renew the temporary trailer permit for an additional 12 months.

From the ordinance

The zoning administrator may grant a temporary permit, issued for a 12-month period, for a mobile home or construction trailer during active construction...