Goochland County Unincorporated, Virginia · General provision

Sec. 15-322.B

Extracted standards

4 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Entrance road base course length50 ft

    The subdivision entrance road, for a distance of 50 feet from the existing edge of pavement, and its associated turn lanes using a minimum of base course pavement.

  • Improvement completion trigger80 pct

    By the earlier of issuance of building permits for 80% of the lots on the plan of development, or 18 months from the recordation of the underlying final plat, the developer must complete all required improvements.

  • Second entrance trigger50 permits

    The second entrance, turn lanes and associated road improvements must be fully installed before the earlier of (a) issuance of the 50th building permit or (b) if phased plans, before the total number of issued building permits in the subdivision exceeds 49.

Signage

From the ordinance

Prior to issuance of a building permit for any structure, the following access improvements must be installed... The subdivision entrance road, for a distance of 50 feet from the existing edge of pavement... By the earlier of issuance of building permits for 80% of the lots on the plan of development, or 18 months from the recordation of the underlying final plat, the developer must complete all required improvements... the second entrance, turn lanes and associated road improvements must be fully installed before the earlier of (a) issuance of the 50th building permit or (b) if phased plans, before the total number of issued building permits in the subdivision exceeds 49.
Sec. 15-322.B