Chesapeake, Virginia · General provision

§ 13-602.B.4.c

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Decision timeline for administrative review-eligible projects150 days

    For a new structure within the lesser of one hundred fifty (150) days of receipt of the completed application or the period required by federal law for such approval or disapproval

  • Decision timeline for co-location of wireless facility90 days

    For the co-location of any wireless facility that is not a small cell facility, within the lesser of ninety (90) days of receipt of a completed application, or the period required by federal law for such approval.

From the ordinance

Within ten (10) days after receipt of an application and a valid electronic mail address for the applicant, the locality shall notify the applicant by electronic mail whether the application is incomplete and specify any missing information; otherwise, the application shall be deemed complete. All such applications shall be approved or denied within the following specified time periods: (i) For a new structure within the lesser of one hundred fifty (150) days of receipt of the completed application or the period required by federal law for such approval or disapproval; or (ii) For the co-location of any wireless facility that is not a small cell facility, within the lesser of ninety (90) days of receipt of a completed application, or the period required by federal law for such approval.
§ 13-602.B.4.c