Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Land reservation hold time18 months
They shall not be required to hold the land longer than 18 months following the recording of the plat
- Reimbursement profit cap10 pct
Not more than ten percent profit on the total of such costs
From the ordinance
Subdividers shall not be required to dedicate land for parks or playgrounds... without reimbursement... Not more than ten percent profit on the total of such costs... They shall not be required to hold the land longer than 18 months following the recording of the plat