Extracted standards
4 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Special useConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. discontinuance period2 years
any use established pursuant to an approved special use permit shall not be reestablished if replaced by a different use or if discontinued for a continuous period of two years or longer.
- Special use permitConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. expiration1 years
An approved special use permit shall become null and void if no application for a building permit to construct the authorized improvements has been submitted within one year of the date of approval by the council.
- Special useConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. reconsideration period1 years
Whenever a special use permit application is denied, substantially the same application shall not be considered again by the council within one year from the date of denial.
- Special useConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. violation cure period90 days
such permit may be subject to revocation if the violation is not corrected within 90 days of written notice to the owner of the property by the zoning administrator.
From the ordinance
An approved special use permit shall become null and void if no application for a building permit to construct the authorized improvements has been submitted within one year of the date of approval by the council.